hard · Project Management Professional predictive
Cinderwell Water is installing a new fleet management system. There is a 0.20 risk of software bugs causing a $30,000 rework. Option A (Extra QA) costs $4,000 and reduces p to 0.05. Option B (Bug Bounty) costs $2,000 and reduces impact to $5,000.
What should the PM do?
- Ignore the bugs as they are a standard part of software development.
- Implement Option A.
- Implement Option B.
- Reassign the project to an agile delivery model to handle bugs better.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?