medium · Project Management Professional Predictive (Plan-Driven)
Ironvale Grid’s PMO has implemented an AI-driven tool that automatically tags and summarizes lessons learned. A project manager notices the tool has miscategorized a safety violation as a 'scheduling delay.'
What should the PM do?
- Escalate the miscategorization to the Ethics Committee as a potential data breach.
- Ask the team to ignore the summary and rely only on the raw meeting notes.
- Manually correct the entry to ensure data integrity and report the tool's error to the PMO.
- Leave the entry as is, since the AI model was approved by the organization's IT governance.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards