Ironvale Grid’s PMO has implemented an AI-driven tool that automatically tags and summarizes lessons learned. A project manager notices the tool has miscategorized a safety violation as a 'scheduling delay.'

What should the PM do?

  1. Escalate the miscategorization to the Ethics Committee as a potential data breach.
  2. Ask the team to ignore the summary and rely only on the raw meeting notes.
  3. Manually correct the entry to ensure data integrity and report the tool's error to the PMO.
  4. Leave the entry as is, since the AI model was approved by the organization's IT governance.