A project manager at Trestle Ports is managing a project with several different workstreams. One workstream is consistently reporting 'Green' status, but the project manager's independent audit shows that several key safety deliverables have been skipped.

What should the PM do?

  1. Publicly call out the workstream lead in the next status meeting for the misleading reporting.
  2. Meet privately with the workstream lead to discuss the discrepancy and the missing safety deliverables.
  3. Escalate the false reporting to the workstream lead's functional manager as a code of conduct violation.
  4. Trust the workstream lead's reporting since they are the subject matter experts.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards