A Larkspur Health project is deploying a new EMR system. A group of surgeons requests a custom dashboard. The PM documents the request and finds it will cost 15,000. The project's contingency reserve is 20,000.

What should the PM do next?

  1. Analyze the impact on the schedule baseline and the risk register.
  2. Approve the change immediately since there is enough contingency reserve.
  3. Ask the surgeons to prioritize the dashboard features using a MoSCoW model.
  4. Reject the surgeons' request and tell them to wait for the maintenance phase.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials