medium · Project Management Professional predictive
A Larkspur Health project is deploying a new EMR system. A group of surgeons requests a custom dashboard. The PM documents the request and finds it will cost 15,000. The project's contingency reserve is 20,000.
What should the PM do next?
- Analyze the impact on the schedule baseline and the risk register.
- Approve the change immediately since there is enough contingency reserve.
- Ask the surgeons to prioritize the dashboard features using a MoSCoW model.
- Reject the surgeons' request and tell them to wait for the maintenance phase.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?