KomFi. Academy

medium · Project Management Professional Predictive (Plan-Driven)

During a night shift at Valeport Energy, the PM discovers that lighting in the main work area is below the OSHA standard. The shift lead says that adding more lights will take four hours and stop the shift's progress.

What should the PM do?

  1. Collaborate with the shift lead to identify only the most critical areas that need more light.
  2. Ask the team to work 'extra carefully' until the lighting can be improved tomorrow.
  3. Document the lighting level in the issues log and report it to the safety officer in the morning.
  4. Direct the shift lead to stop work and install proper lighting before anyone continues.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards