medium · Project Management Professional predictive

During a night shift at Valeport Energy, the PM discovers that lighting in the main work area is below the OSHA standard. The shift lead says that adding more lights will take four hours and stop the shift's progress.

What should the PM do?

  1. Collaborate with the shift lead to identify only the most critical areas that need more light.
  2. Ask the team to work 'extra carefully' until the lighting can be improved tomorrow.
  3. Document the lighting level in the issues log and report it to the safety officer in the morning.
  4. Direct the shift lead to stop work and install proper lighting before anyone continues.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials