medium · Project Management Professional Predictive (Plan-Driven)
During a night shift at Valeport Energy, the PM discovers that lighting in the main work area is below the OSHA standard. The shift lead says that adding more lights will take four hours and stop the shift's progress.
What should the PM do?
- Collaborate with the shift lead to identify only the most critical areas that need more light.
- Ask the team to work 'extra carefully' until the lighting can be improved tomorrow.
- Document the lighting level in the issues log and report it to the safety officer in the morning.
- Direct the shift lead to stop work and install proper lighting before anyone continues.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?