Bramble Civic is building a new municipal center. During a quality audit, the auditor finds that the concrete pouring process consistently misses the required temperature threshold, though the final slabs have passed all strength tests so far.

What should the project manager do?

  1. Submit a change request to lower the temperature threshold in the quality management plan.
  2. Continue the work as planned since the deliverables meet the final acceptance criteria.
  3. Facilitate a root cause analysis with the team to identify why the process is non-compliant and implement a preventive action.
  4. Instruct the quality control team to increase the frequency of strength testing on the poured slabs, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials