medium · Project Management Professional predictive
Bramble Civic is building a new municipal center. During a quality audit, the auditor finds that the concrete pouring process consistently misses the required temperature threshold, though the final slabs have passed all strength tests so far.
What should the project manager do?
- Submit a change request to lower the temperature threshold in the quality management plan.
- Continue the work as planned since the deliverables meet the final acceptance criteria.
- Facilitate a root cause analysis with the team to identify why the process is non-compliant and implement a preventive action.
- Instruct the quality control team to increase the frequency of strength testing on the poured slabs, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?