Nimbus Clinics is managing a facility renovation. The project manager holds a monthly steering committee meeting. Several members complain that they are receiving too many technical details and not enough information on strategic milestone progress.

What should the project manager do?

  1. Tell the committee that the technical details are necessary for transparency and audit compliance.
  2. Review and update the communications management plan to ensure reports are tailored to each stakeholder group's specific information needs.
  3. Invite the steering committee to the daily team standups so they can see the technical work for themselves, after reviewing the current risk register entries.
  4. Stop sending detailed reports and only provide a high-level summary to all stakeholders going forward.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards