hard · Project Management Professional predictive
Kestrel Civic is conducting the final procurement audit for a predictive construction project. The contractor finished on time and on budget but refused to participate in the 'Lessons Learned' session, citing that their contract does not require it.
What should the project manager do?
- Update the contractor's contract mid-closure to include the requirement for lessons learned participation.
- Conduct the procurement audit using internal documentation and record the contractor’s lack of participation in the vendor performance file.
- Withhold the final payment until the contractor agrees to participate in the session to ensure organizational learning, after reviewing the current risk register entries.
- Escalate the issue to the procurement officer and request that the contractor be blacklisted from future projects.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?