hard · Project Management Professional predictive

A project manager at Marrowfield Labs is pressured by the project sponsor to report that a key milestone has been achieved, even though the final quality tests are still 3 days from completion.

What should the project manager do?

  1. Ask the quality manager to sign off on the milestone early so the project manager can report it as complete truthfully.
  2. Refuse to report the milestone as achieved and explain the ethical requirement for honest status reporting.
  3. Report the milestone as achieved but add a small footnote stating that the quality tests are still in progress.
  4. Report the milestone as achieved and explain that the quality tests are a mere formality that will be finished shortly.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials