medium · Project Management Professional Predictive (Plan-Driven)
An Ironvale Grid project is falling behind because the 'Bus Factor' for the environmental permitting task is exactly 1. The permit lead is the only person who understands the local municipal nuances.
What should the project manager do first?
- Update the Risk Register to reflect the high probability of a schedule delay.
- Schedule a series of facilitated sessions where the permit lead mentors a backup team member.
- Escalate to the Permitting Department to request additional certified staff.
- Direct the permit lead to create a comprehensive wiki of all local regulations, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards