medium · Project Management Professional predictive

An Ironvale Grid project is falling behind because the 'Bus Factor' for the environmental permitting task is exactly 1. The permit lead is the only person who understands the local municipal nuances.

What should the project manager do first?

  1. Update the Risk Register to reflect the high probability of a schedule delay.
  2. Schedule a series of facilitated sessions where the permit lead mentors a backup team member.
  3. Escalate to the Permitting Department to request additional certified staff.
  4. Direct the permit lead to create a comprehensive wiki of all local regulations, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials