hard · Project Management Professional predictive
Stonehaven Transit is managing an identified risk that has just occurred: a key supplier has declared bankruptcy. The risk register includes a planned response: 'Purchase the specialized components from an alternate vendor using the contingency reserve.'
What should the project manager do first?
- Perform a new qualitative risk analysis on the alternate vendor's reliability.
- Submit a change request to the Change Control Board to access management reserve for the new vendor.
- Request the sponsor's permission to terminate the contract with the bankrupt supplier.
- Implement the planned response and move the risk to the issue log.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?