Amberline Transit has two senior engineers who disagree on the technical architecture for a new light rail sensor. The project is in the early planning phase.

What should the project manager do first?

  1. Escalate the disagreement to the Chief Engineer for a final decision.
  2. Assign the decision to the more senior engineer to avoid further delay.
  3. Log the conflict as a risk and wait for the engineers to reach consensus.
  4. Meet with both engineers together to understand their perspectives.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials