Westfork Municipal is upgrading a predictive water treatment plant. The union plant operator lead will not follow the new ITP for chemical titration, claiming it contradicts his formal training from 10 years ago.

What should the project manager do first?

  1. Provide the lead with a copy of the new regulations that mandated the ITP change.
  2. Request that the union steward attend a meeting to enforce the new operating procedures.
  3. Inform the lead that his prior training is obsolete and he must follow current instructions, after reviewing the current risk register entries.
  4. Compare the new ITP against the old training materials with the lead to identify the specific points of contradiction.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials