hard · Project Management Professional predictive

A team at Willowbrook Schools is frustrated because they are receiving conflicting instructions from the project manager and a senior administrator. This is leading to rework and confusion.

What should the project manager do first?

  1. Update the team charter to state that the project manager is the sole source of instructions for the team.
  2. Instruct the team to ignore the senior administrator's instructions and only follow the project manager's direction.
  3. Meet with the senior administrator to clarify roles and agree on a unified communication path to the team.
  4. Escalate the senior administrator's interference to the school board to protect the project's governance.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials