medium · Project Management Professional Predictive (Plan-Driven)

Valeport Energy is executing a predictive project to build a refinery. The customer refuses to accept a deliverable during the Validate Scope process, claiming it lacks a specific safety shut-off valve.

What should the project manager do first?

  1. Instruct the team to install the valve immediately to satisfy the customer, before confirming the relevant stakeholders agree.
  2. Check the requirements traceability matrix (RTM) to see if the valve was an approved requirement.
  3. Negotiate with the customer to accept the deliverable without the valve.
  4. Submit a change request to add the safety shut-off valve.