hard · Project Management Professional Predictive (Plan-Driven)

A safety inspector at Stonehaven Transit identifies a non-compliant hazardous material storage area. Correcting the issue will cost $12,000 and delay the current phase by one week.

What should the project manager do first?

  1. Immediately stop the hazardous work and secure the area according to the inspector's findings.
  2. Negotiate with the inspector to see if the correction can be deferred until the next phase.
  3. Submit a change request to the CCB to approve the budget and schedule impact of the correction.
  4. Analyze the schedule to see if the one-week delay can be absorbed by existing float.

Sign up free to see the explanation and track your rank →