medium · Project Management Professional predictive

Cinderwell Water is replacing main pipelines. During a quality audit, it is discovered that the team is not following the approved welding inspection procedure, though no defects have been found in the completed work yet.

What should the project manager do first?

  1. Perform root cause analysis to understand why the procedure is not being followed.
  2. Change the welding procedure to match the current team practices. given the information provided
  3. Issue a formal warning to the team members responsible for the welding.
  4. Immediately stop all work on the pipeline until the audit is resolved.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials