KomFi. Academy

medium · Project Management Professional Predictive (Plan-Driven)

At Ironvale Grid, a project manager discovers that a high-priority safety requirement in the project scope statement has no associated test cases in the quality management plan. The project is currently in the late stages of the Executing process group.

What should the project manager do first?

  1. Wait until the Validate Scope process to see if the customer identifies the missing functionality, before confirming the relevant stakeholders agree.
  2. Update the Requirements Traceability Matrix (RTM) and facilitate a session with the quality lead to develop the missing test cases.
  3. Direct the technical team to begin verification testing immediately to identify any defects.
  4. Escalate the issue to the Ironvale Safety Steering Committee as a major compliance risk.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards