At Ironvale Grid, a project manager discovers that a high-priority safety requirement in the project scope statement has no associated test cases in the quality management plan. The project is currently in the late stages of the Executing process group.

What should the project manager do first?

  1. Wait until the Validate Scope process to see if the customer identifies the missing functionality, before confirming the relevant stakeholders agree.
  2. Update the Requirements Traceability Matrix (RTM) and facilitate a session with the quality lead to develop the missing test cases.
  3. Direct the technical team to begin verification testing immediately to identify any defects.
  4. Escalate the issue to the Ironvale Safety Steering Committee as a major compliance risk.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials