Plover Software is delivering a predictive data security project for a bank. During execution, the Chief Information Officer (CIO) requests an additional encryption layer that was not in the original scope.
What should the project manager do first?
- Ask the team to start implementing the new encryption layer
- Inform the CIO that the request cannot be accommodated currently
- Submit a change request directly to the Change Control Board
- Document the request and evaluate its impact on the project
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?