Larkspur Health is delivering a predictive project for a new diagnostic wing. During internal testing, the team discovers a software glitch in the imaging system that requires $5,000 in unplanned labor to fix.

What should the project manager do first?

  1. Escalate the budget variance to the hospital board to request additional contingency.
  2. Update the product backlog and prioritize the fix for the next two-week iteration.
  3. Instruct the lead developer to skip the next round of unit testing to recover the lost time.
  4. Classify the expense as an internal failure cost and proceed with root cause analysis.