On the Harborline Transit predictive signaling project, a project manager discovers that a vendor laptop containing unencrypted Personally Identifiable Information (PII) for 5,000 passengers is missing.

What should the project manager do first?

  1. Escalate the situation to the project sponsor and request additional management reserve for legal fees.
  2. Update the project risk register to reflect the potential for a data privacy lawsuit.
  3. Assess the impact of the lost hardware on the project's critical path and schedule baseline.
  4. Initiate the organization's data breach containment protocol to secure remaining accounts.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials