medium · Project Management Professional Predictive (Plan-Driven)
During the inspection of a new substation at Fenwick Grid, a technician discovers that three circuit breakers fail to trip at the required 150% load capacity. The project manager records this as a nonconforming deliverable.
What should the project manager do next?
- Perform a root cause analysis to identify why the manufacturing process allowed the defect.
- Order the immediate replacement of all breakers from the same vendor without further testing.
- Notify the customer that the substation is ready for the final Validate Scope review.
- Submit a change request for defect repair through the integrated change control process.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards