easy · Project Management Professional predictive

The steering committee at Ironvale Grid is reviewing a project at a kill point. The project manager reports that the technology used is now obsolete, but the project is 90% complete. The committee decides to terminate.

What should the project manager do next?

  1. Finish the remaining 10% of the work anyway to ensure the budget is fully spent
  2. Follow the 'Close Project or Phase' process, including capturing lessons learned and archiving records
  3. Delete all project files to save server space since the project will not be used, after reviewing the current risk register entries.
  4. Ask the team to ignore the committee and continue working in secret

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials