medium · Project Management Professional predictive
At Westfork Municipal, a civic center renovation is under a predictive BAC of 6,000,000. The AC is 3,500,000 and EV is 3,000,000. The project manager calculates the TCPI and realizes the team needs to improve efficiency from 0.86 to 1.20.
What should the project manager do next?
- Immediately update the EAC to 7,000,000 and inform the City Manager of the 1,000,000 overrun, before confirming the relevant stakeholders agree.
- Consult with the team to identify specific process improvements or efficiencies to bridge the 0.34 gap.
- Create a burn-down chart to visualize the remaining points and TCPI trajectory.
- Direct the team to skip quality audits for the next phase to reduce costs and lower the TCPI.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?