medium · Project Management Professional Predictive (Plan-Driven)

At Westfork Municipal, a civic center renovation is under a predictive BAC of 6,000,000. The AC is 3,500,000 and EV is 3,000,000. The project manager calculates the TCPI and realizes the team needs to improve efficiency from 0.86 to 1.20.

What should the project manager do next?

  1. Immediately update the EAC to 7,000,000 and inform the City Manager of the 1,000,000 overrun, before confirming the relevant stakeholders agree.
  2. Consult with the team to identify specific process improvements or efficiencies to bridge the 0.34 gap.
  3. Create a burn-down chart to visualize the remaining points and TCPI trajectory.
  4. Direct the team to skip quality audits for the next phase to reduce costs and lower the TCPI.

Sign up free to see the explanation and track your rank →