easy · Project Management Professional predictive

A predictive project at Redcedar Energy experiences a delay in a non-critical activity. The activity has 10 days of total float and is forecast to finish 4 days late.

What should the project manager do next?

  1. Update the schedule model to reflect the new dates and continue monitoring.
  2. Fast track the subsequent activities to ensure the path regains its original float.
  3. Submit a change request to the Change Control Board to extend the schedule baseline.
  4. Authorize the team to work overtime on the activity to recover the lost 4 days.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials