A predictive project at Redcedar Energy experiences a delay in a non-critical activity. The activity has 10 days of total float and is forecast to finish 4 days late.
What should the project manager do next?
- Update the schedule model to reflect the new dates and continue monitoring.
- Fast track the subsequent activities to ensure the path regains its original float.
- Submit a change request to the Change Control Board to extend the schedule baseline.
- Authorize the team to work overtime on the activity to recover the lost 4 days.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?