medium · Project Management Professional predictive

Trestle Ports is managing a construction project. A stakeholder complains that they were unaware of a major site closure that affected their operations. A review shows that the site closure was listed in the status report emailed to all stakeholders.

What should the project manager do?

  1. Meet with the stakeholder to understand their specific communication preferences and update the communications management plan accordingly.
  2. Post all site closure notices on the project's internal wiki page and assume all stakeholders will check it daily, while documenting the decision in the issue log.
  3. Send a follow-up email with the site closure notice highlighted in the subject line.
  4. Explain to the stakeholder that they are responsible for reading all project status reports sent to them.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials