At Ironvale Grid, a predictive project is nearing its second phase gate. The project manager's data shows the project is 10% over budget but is still forecast to meet all business case benefits.

What should the project manager present at the gate?

  1. Nothing, since the project is only 10% over and it does not meet the escalation threshold
  2. A plan to use the management reserve to hide the cost variance from the committee
  3. The current variance, the root cause, and a forecast showing that the benefits still justify the increased cost
  4. A request for a 'Go' decision while promising the team will work overtime for free to recover the costs, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials