At Ironvale Grid, a predictive project is nearing its second phase gate. The project manager's data shows the project is 10% over budget but is still forecast to meet all business case benefits.

What should the project manager present at the gate?

  1. Nothing, since the project is only 10% over and it does not meet the escalation threshold
  2. A plan to use the management reserve to hide the cost variance from the committee
  3. The current variance, the root cause, and a forecast showing that the benefits still justify the increased cost
  4. A request for a 'Go' decision while promising the team will work overtime for free to recover the costs, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards