hard · Project Management Professional Predictive (Plan-Driven)

A safety auditor at Stonehaven Transit has been praised for their attention to detail but is frequently in conflict with site supervisors. The auditor wants to move into a Stakeholder Management role eventually.

What should the project manager prioritize during their next one-on-one?

  1. Train the auditor in the latest 'Conflict Resolution' frameworks.
  2. Coach the auditor on their specific interactions with the site supervisors.
  3. Direct the auditor to focus on reducing the number of safety infractions found, after reviewing the current risk register entries.
  4. Mentor the auditor on building influence and managing organizational power dynamics.