easy · Project Management Professional predictive

Osprey Bank's project manager is updating the project status. The automated dashboard shows that the project is on track (Green), but the team leads have informed her that a key security approval is likely to be delayed by two weeks.

What should the project manager report?

  1. Wait until the delay actually occurs before changing the status to Red.
  2. Report Green status to match the automated dashboard.
  3. Report the potential delay and the risks to the current status.
  4. Instruct the team to work overtime to ensure the dashboard stays Green.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials