Kestrel Civic is overseeing a bridge renovation. The inspection log shows 200 defects: Weld Porosity (90), Rebar Misplacement (70), Surface Pitting (25), and Paint Overspray (15). The project manager wants to perform Manage Quality.

What should they do?

  1. Create a scatter diagram to see the relationship between humidity and paint overspray.
  2. Ask the team to add extra weld layers to all joints to ensure they exceed the safety requirements, while documenting the decision in the issue log.
  3. Investigate the root causes of Weld Porosity and Rebar Misplacement to improve the construction process.
  4. Perform a 100% inspection of the bridge and log all defects in the issue log for repair.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards