Bramble Civic is planning a new park construction. The Project Charter contains a summary milestone schedule.
Where should the project manager place the detailed, time-phased schedule and baselines?
- The Project Management Plan.
- The Product Backlog.
- The Project Charter.
- The Risk Register.