Fenwick Grid is closing a power-line project. The project manager is summarizing the 'Sustainability' outcomes. The project reduced carbon emissions by 22%, exceeding the target of 15%.
Where should this be documented?
- In the final report as a summary of benefits realization.
- In the next project's business case to prove the technology works.
- In the charter, to update the high-level description.
- In the risk register as a 'positive risk' that was realized.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards