A massive unexpected flood has damaged the construction site at Redcedar Energy. This specific risk was not identified in the risk register. The project manager must access additional funds to resume work.
Which action is most appropriate?
- Use the project's contingency reserve to cover the repairs immediately.
- Explain to the stakeholders that since the risk wasn't identified, the project cannot proceed.
- Request a new bottom-up estimate for the entire project from the engineering team.
- Submit a change request to the sponsor to access the management reserve.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?