easy · Project Management Professional predictive

A project manager at Harborline Transit is preparing for a meeting. They notice that the language barrier between two team leads is causing significant 'noise' in their email exchanges.

Which action should the project manager take to ensure effective communication?

  1. Facilitate an interactive video call where concepts can be clarified in real-time with visual aids.
  2. Escalate the language barrier issue to the HR department as a performance concern, while documenting the decision in the issue log.
  3. Assign a translator to rewrite every email sent between the two leads.
  4. Instruct both leads to only communicate through formal, written memos.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials