medium · Project Management Professional predictive
A critical path at Kestrel Civic has three activities. A: σ^2=1, B: σ^2=4, C: σ^2=4. The project manager is asked to reduce path uncertainty.
Which activity's variance reduction would have the greatest impact on σ_path?
- The activity with the longest expected duration, regardless of its variance.
- Activity A, because its variance is already the lowest.
- Activities B or C, because they contribute more to the sum of variances.
- All activities have an equal impact because standard deviations are additive.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?