Cinderwell Water is installing a SCADA system. A cyberattack risk has p=0.15 and I=$400,000. Option A (Firewall) costs $30,000 and reduces p to 0.05. Option B (Cyber Insurance) costs $10,000 and reduces impact to $50,000.
Which approach is more efficient?
- Option B.
- Option A.
- Neither, as the project should use management reserve when the event occurs.
- The project manager should use the Delphi technique to reassess the probability.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?