hard · Project Management Professional Predictive (Plan-Driven)

At Nimbus Clinics, a project manager is concluding a multi-year project. Several team members have been with the project since the start, and as it winds down, productivity has dropped and morale is low.

Which leadership action is most appropriate during 'Adjourning'?

  1. Host a celebration of the project’s successes, recognize individual contributions, and support the team’s transition to new roles.
  2. Conduct a mandatory retrospective focusing on why productivity dropped in the final month to identify performance gaps, while documenting the decision in the issue log.
  3. Implement a performance-based bonus system for the final month to incentivize the completion of closure tasks.
  4. Reassign the team to new projects immediately to prevent further productivity loss and minimize overhead costs.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards