Stonehaven Transit is replacing rail ties. The critical path is delayed. The project manager crashes the project.

Which metric will most likely show a negative variance as a result?

  1. To-Complete Performance Index (TCPI).
  2. Estimate to Complete (ETC).
  3. Cost Variance (CV).
  4. Schedule Performance Index (SPI).