A project manager at Harborline Transit is finalizing the monthly status report. They want to ensure it is 'clear, concise, and coherent.'

Which principle of communication are they applying?

  1. The Active Listening framework
  2. Interactive communication guidelines
  3. The Sender's Responsibility model
  4. The 5C's of written communication