KomFi. Academy

hard · Project Management Professional Predictive (Plan-Driven)

Hearthline Energy is conducting a quality audit on the turbine assembly process. This audit identifies that several technicians are skipping the final calibration check.

Which process is being performed, and what is the outcome?

  1. Manage Quality; the outcome is a change request to improve the process or provide training.
  2. Control Quality; the outcome is a defect repair for the turbines skipped in calibration.
  3. Validate Scope; the outcome is the formal acceptance of the calibrated turbines.
  4. Plan Quality Management; the outcome is an updated quality management plan.