medium · Project Management Professional predictive
Hearthline Energy is conducting an environmental impact project. The project manager wants to ensure that the work performed aligns with the approved scope and catches any 'gold plating.'
Which process should they focus on?
- Define Scope
- Validate Scope
- Control Quality
- Control Scope