hard · Project Management Professional predictive

Cinderwell Water is building Mainline 500. A utility strike risk has p=0.40 and I=$50,000. Option A (Potholing) costs $12,000 and reduces p to 0.05. Option B (Sewer Mapping) costs $6,000 and reduces impact to $10,000.

Which response is better?

  1. Accept the risk as potholes are unavoidable in civil engineering.
  2. Select Option B.
  3. Option A.
  4. Option B.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials