medium · Project Management Professional predictive
The project manager at Valeport Energy has identified a risk that a critical specialized technician might be unavailable. The PM decides to purchase an insurance policy to cover the cost of a last-minute replacement.
Which risk response strategy is this?
- Avoid.
- Mitigate.
- Transfer.
- Accept.