easy · Project Management Professional predictive
The project manager at Fenwick Grid has finally diagnosed the planner's underperformance as a 'Skill' gap. They decide to provide 'Training'.
Which rule should they follow regarding the timing of this training?
- The rule of 'Wait until the next phase' to avoid disrupting the current execution, before confirming the relevant stakeholders agree.
- The rule of 'Prevention over correction' - training should happen as soon as a gap is identified to avoid future baseline breaches.
- The rule of 'Only train on the team's personal time' to save project costs.
- The rule of 'Never train an underperformer' until they show improved will.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?