A project manager at Valeport Energy is crashing the schedule. They have two options: Activity X saves 1 week for 10,000. Activity Y saves 1 week for15,000. However, Activity X is on a path with 2 weeks of float, and Activity Y is on the critical path.

Which should be crashed?

  1. Activity Y, because it is on the critical path.
  2. Both activities, to ensure the schedule is compressed safely.
  3. Activity X, because it is cheaper.
  4. Neither; the project manager should wait until the critical path shifts to Activity X.