medium · Project Management Professional Predictive (Plan-Driven)
A project manager at Valeport Energy is crashing the schedule. They have two options: Activity X saves 1 week for 10,000. Activity Y saves 1 week for15,000. However, Activity X is on a path with 2 weeks of float, and Activity Y is on the critical path.
Which should be crashed?
- Activity Y, because it is on the critical path.
- Both activities, to ensure the schedule is compressed safely.
- Activity X, because it is cheaper.
- Neither; the project manager should wait until the critical path shifts to Activity X.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards