medium · Project Management Professional predictive

A project manager at Valeport Energy is crashing the schedule. They have two options: Activity X saves 1 week for 10,000. Activity Y saves 1 week for15,000. However, Activity X is on a path with 2 weeks of float, and Activity Y is on the critical path.

Which should be crashed?

  1. Activity Y, because it is on the critical path.
  2. Both activities, to ensure the schedule is compressed safely.
  3. Activity X, because it is cheaper.
  4. Neither; the project manager should wait until the critical path shifts to Activity X.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials