Kestrel Civic has two potential site locations. Site X has a 0.10 probability of a -$200,000 cleanup cost. Site Y has a 0.50 probability of a -$30,000 extra foundation cost.
Which site is preferred based on EMV?
- Site Y
- Hire a consultant to decide.
- Site X
- Either, since the differences are negligible.