medium · Project Management Professional predictive
During a network analysis at Solstice Labs, a project manager finds an activity with a free float of 4 days and a total float of 10 days. The activity is delayed by 6 days.
Which statement is true?
- The project completion date will be delayed by 2 days.
- The activity is on the critical path.
- Neither the successor nor the project finish will be affected, after reviewing the current risk register entries.
- The project completion date will not change, but the start of the successor activity will be delayed.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?