During a network analysis at Solstice Labs, a project manager finds an activity with a free float of 4 days and a total float of 10 days. The activity is delayed by 6 days.

Which statement is true?

  1. The project completion date will be delayed by 2 days.
  2. The activity is on the critical path.
  3. Neither the successor nor the project finish will be affected, after reviewing the current risk register entries.
  4. The project completion date will not change, but the start of the successor activity will be delayed.