medium · Project Management Professional predictive

During a network analysis at Solstice Labs, a project manager finds an activity with a free float of 4 days and a total float of 10 days. The activity is delayed by 6 days.

Which statement is true?

  1. The project completion date will be delayed by 2 days.
  2. The activity is on the critical path.
  3. Neither the successor nor the project finish will be affected, after reviewing the current risk register entries.
  4. The project completion date will not change, but the start of the successor activity will be delayed.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials