Whitlock Software's PM decides to 'pair program' for the most complex parts of the migration. While it doubles the immediate labor cost, it is expected to eliminate 90% of downstream defects. This labor cost is:

  1. Scope creep
  2. Appraisal cost
  3. Internal failure cost
  4. Prevention cost