easy · Project Management Professional hybrid
A transit engineer at Stonehaven Transit has a high school diploma (EQF 4) and an active CAPM. They have been leading small infrastructure upgrades for 5 years (60 months).
Do they meet the eligibility requirements?
- No, they need a university degree to apply for the PMP.
- Yes, they have met the 60-month Tier 1 requirement and the active CAPM waives the training.
- Yes, but they must first escalate to PMI to convert their CAPM to a PMP automatically.
- No, they must complete a 35-hour course because the CAPM waiver only applies to degree holders.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?