Kestrel Civic is constructing a municipal center using a hybrid approach. The S-curve for the predictive phase shows the EV line below the PV line, and the AC line above both.

What should the project manager investigate first?

  1. The Kestrel Civic steering committee's willingness to accept a lower quality grade.
  2. The possibility of moving all remaining work to a Scrum backlog to save costs.
  3. The root cause of the schedule delay and the cost inefficiency.
  4. The procurement team's ability to fast-track the remaining materials.

Sign up free to see the explanation and track your rank →